Assessing the Impact of Temporary Generators on Neighboring Areas in Kuwait: How Do You Manage Nuisance and Emissions During a Project?
24 Aug

Assessing the Impact of Temporary Generators on Neighboring Areas in Kuwait: How Do You Manage Nuisance and Emissions During a Project?

Monday August 24th, 2026

An assessment of the impact of temporary generators on neighboring areas in Kuwait helps determine whether the generator’s location and operating method may cause noise, vibration, or exhaust emissions that affect nearby buildings, workers, or users. The solution is not limited to moving the generator a few meters away; it also includes location selection, exhaust direction, operating hours, acoustic barriers, maintenance, complaint monitoring, and measurements where necessary.

In construction, maintenance, and renovation projects, a temporary generator may be necessary to provide power. However, “temporary” does not mean that its environmental or operational impact can be ignored. A generator operating for long hours near an occupied building may become a recurring source of disturbance even if it is only used for a few weeks.

Quick Answer: Why Is It Important to Assess the Impact of Temporary Generators on Neighboring Areas in Kuwait?

The assessment helps identify potential nuisance and emissions before operation begins, select a location that reduces the transmission of noise and exhaust to nearby buildings and areas, and establish clear procedures for operation, maintenance, and complaint response.

The assessment becomes particularly important when the generator is close to residences, offices, hotels, healthcare facilities, building entrances, or areas used by the public. It is also useful for projects requiring night-time or extended operation or using more than one generator simultaneously.

There is no single spatial rule that suits every case. The appropriate distance and control method are influenced by generator capacity, operating hours, site design, exhaust direction, surrounding conditions, and applicable regulatory requirements.

Quick Answer: When Does a Project Need Environmental Consultancy in Kuwait?

A project may need environmental consultancy when generators operate close to occupied buildings, when noise or exhaust-odor complaints recur, when monitoring procedures are unclear, or when extended or night-time operation is required.

Consultancy may also be appropriate when establishing a new project, expanding an existing facility, relocating a generator, increasing the number of units, or reviewing environmental compliance and the Health, Safety and Environment Plan.

The quality of environmental consultancy depends on understanding the nature of the activity and its regulatory requirements. Environmental requirements vary according to the sector, project size, and location. Therefore, the scope of work should be determined after reviewing site details, equipment, operating periods, and the regulatory authorities associated with the project.

What Is Meant by Assessing the Impact of Temporary Generators on Neighboring Areas?

It is a structured review of the installation and operation of temporary generators to identify potential effects on the surrounding environment, workers, and nearby users.

The assessment usually covers several areas:

  • Generator location relative to buildings.
  • Proximity to windows, doors, and entrances.
  • Relationship to air intakes and ventilation systems.
  • Exhaust discharge direction.
  • Expected or measured noise level.
  • Vibration transmitted through floors or foundations.
  • Number of operating hours.
  • Daytime or night-time operation.
  • Generator capacity and engine condition.
  • Fuel consumption and refueling method.
  • Preventive maintenance.
  • Presence of visible smoke or unusual odors.
  • Acoustic barriers or enclosures used.
  • Presence of nearby residential or commercial areas.
  • Complaint and observation records.
  • Emergency procedures and spill response.

The objective is not merely to identify the existence of a noise or exhaust source, but to understand who may be affected, when they may be affected, through what pathway, and what practical measure can best reduce the impact.

Why Can a Temporary Generator Become a Problem for Neighboring Areas?

A generator is often viewed simply as another piece of project equipment, similar to a crane or compressor. However, its operating characteristics are different because it may run continuously for hours, sometimes throughout an entire shift or during the night.

Problems usually arise through four main pathways.

Continuous Noise

Noise from the engine, fan, and exhaust can become a recurring nuisance, particularly when the generator operates near occupied building façades or during rest periods.

Vibration

Vibration may be transmitted through the generator base or the surface on which it is installed, potentially causing disturbance inside a nearby building even when the external noise level does not appear unusually high.

Exhaust Emissions

Generator engines produce combustion emissions. The issue may become more noticeable when the exhaust outlet is close to a building, gathering area, or movement route, or when wind direction carries the exhaust toward nearby receptors.

Operation and Poor Maintenance

A generator operating in poor condition may produce unusual smoke, stronger odors, or additional mechanical noise. This makes maintenance part of environmental management rather than merely a technical equipment requirement.

The Kuwait Environment Public Authority indicates that air-quality monitoring responsibilities include noise and ambient air monitoring, complaint investigation, and ensuring compliance with applicable limits and standards in the relevant executive regulations. Emission monitoring also includes stationary and mobile sources and the review of their records and reports.

When Does a Project Need an Assessment of Temporary Generators?

When Establishing a New Project

Generator locations should preferably be identified during site planning rather than selecting whatever space remains after offices, storage areas, and equipment routes have already been allocated.

Early selection allows the project to review:

  • Nearest buildings.
  • Access routes.
  • Exhaust direction.
  • Electrical cable distance.
  • Fuel routes.
  • Work areas.
  • Possibility of installing barriers.
  • Future project requirements.

When Expanding an Existing Facility

A new section may be constructed while the original facility remains operational. In this case, the generator’s effect on employees, customers, and existing operations should be assessed, not only its effect on the construction workforce.

When Developing an Industrial Site

Multiple existing noise and emission sources may already be present. Therefore, the generator should be considered within the overall operating environment rather than assuming its impact is separate from other equipment.

When Relocating a Generator

The same generator may be acceptable in one location and problematic in another. Proximity to a building, changes in exhaust direction, or different operating hours can alter its level of impact.

When Increasing the Number of Generators

Operating two or more units side by side may increase nuisance levels and the overall environmental load, requiring a reassessment of barriers, distribution, and operating hours.

When Reviewing Environmental Compliance

Project management may need to confirm that actual operations comply with the HSE Plan, Environmental Management Plan, project requirements, and relevant environmental conditions.

When Improving Performance and Sustainability

The assessment may reveal that a generator larger than required is operating at low loads for long periods, or that smaller units could be distributed or managed more efficiently depending on the project’s technical requirements.

How Do You Select the Location of a Temporary Generator?

Location selection is the first and most important preventive measure.

Start With Sensitive Receptors, Not With the Generator

Before choosing the generator location, identify what surrounds it:

  • Residences.
  • Offices.
  • Hotels.
  • Schools.
  • Clinics or hospitals.
  • Restaurants.
  • Rest areas.
  • Meeting rooms.
  • Worker accommodation.
  • Main entrances.
  • Openable windows.
  • Air-intake openings.

Then ask: If the generator is installed here, where will the noise and exhaust travel?

Do Not Rely on Distance Alone

Increasing distance generally helps reduce impact, but it is not the only factor.

A generator that is slightly farther away but has its exhaust directed toward a ventilation intake may be more problematic than a closer generator whose exhaust is appropriately directed away.

Therefore, location assessment should combine:

Distance + Exhaust Direction + Barriers + Operating Hours + Wind Direction + Building Characteristics.

Review Roofs and Confined Spaces

A generator should not be placed in a location where exhaust can accumulate or re-enter work areas or buildings.

Similarly, placing a generator between high walls may alter the way sound and exhaust disperse. The actual location should therefore be assessed rather than assuming that surrounding walls always provide better protection.

Review Maintenance and Refueling Access

An environmentally suitable location must also be practical. The team needs sufficient space for access, maintenance, refueling, and safe management of any spill without obstructing exits or emergency routes.

How Can You Reduce Noise Nuisance From Temporary Generators?

  1. Increase Separation From Neighboring Areas Where Possible

Where a generator can be moved farther away from sensitive areas without compromising safe operation, this option should be assessed first.

  1. Use an Acoustic Enclosure or Sound-Attenuated Canopy

Generators designed with acoustic enclosures may offer a significant improvement compared with open units, provided that the enclosure remains intact and has not been modified in a way that reduces its effectiveness.

  1. Use Acoustic Barriers

A barrier may reduce sound transmission when its height and location are properly selected.

However, an incorrectly designed barrier may:

  • Leave a direct sound path.
  • Reflect noise toward another building.
  • Obstruct ventilation.
  • Increase generator temperature.
  • Restrict maintenance access.

Manufacturer requirements, safety, and ventilation therefore need to be considered alongside the acoustic objective.

  1. Control Vibration

Suitable vibration-isolation mounts or bases may be used according to the equipment and installation conditions, while ensuring that the support is stable and does not transmit vibration to nearby structures.

  1. Manage Operating Hours

If night-time operation is unnecessary, changing the operating schedule may be one of the most effective measures for reducing disturbance to neighboring areas.

If night operation is required, monitoring should be increased and the need for additional controls assessed.

  1. Maintain the Generator

Damage to the fan, engine components, exhaust system, or enclosure may increase noise above the normal operating condition.

A documented maintenance schedule helps distinguish between normal generator noise and an abnormal condition requiring intervention.

  1. Take Measurements When Necessary

Noise cannot always be evaluated by hearing alone. Some cases may require measurements at points representative of neighboring areas or project boundaries, particularly when complaints occur, operation is prolonged, or sensitive receptors are present.

The Kuwait Environment Public Authority refers to monitoring noise data, reviewing reports, investigating complaints, and applying the standards and limits contained in the executive regulations of the Environmental Protection Law.

How Do You Manage Exhaust Emissions?

Check the Exhaust Pipe Direction

Avoid directing exhaust toward:

  • Doors.
  • Windows.
  • Air-intake openings.
  • Gathering areas.
  • Pedestrian routes.
  • Vehicle waiting areas.
  • Site offices.
  • Nearby buildings whenever technically feasible.

Monitor Wind Direction

An exhaust direction that is acceptable under normal conditions may become problematic when the wind changes.

It is therefore useful to record:

  • Wind direction in operational terms.
  • Time of the complaint.
  • Ongoing activity.
  • Generator operating status.
  • Areas where odors were observed.

Monitor Visible Smoke

Unusual visible smoke should trigger a technical inspection and should not automatically be treated as normal merely because the generator operates on diesel.

It may be related to maintenance, engine condition, load, or fuel, and the cause should be assessed by qualified personnel.

Maintain Preventive Maintenance

A maintenance program helps improve combustion conditions and reduce faults that may increase smoke, odors, or noise.

Depending on the project system, the generator log should include:

  • Operating hours.
  • Date of last maintenance.
  • Daily inspection.
  • Exhaust observations.
  • Faults.
  • Replacement of filters and consumables according to manufacturer instructions.
  • Corrective actions.

Avoid Unnecessary Operation

Operating a generator during periods when there is no actual electrical demand increases fuel use, emissions, and noise without providing an operational benefit.

The operating schedule can be reviewed to determine whether shutdown during certain periods is technically and operationally possible.

Why Should Noise and Exhaust Be Managed Together?

One common mistake is solving one problem in a way that worsens another.

For example, a generator may be enclosed too tightly to reduce noise, resulting in inadequate ventilation or altered exhaust dispersion.

Similarly, an exhaust pipe may be extended or modified without assessing how the change affects generator performance and manufacturer requirements.

The design should therefore integrate:

  • Noise control.
  • Ventilation.
  • Heat management.
  • Exhaust discharge.
  • Maintenance access.
  • Fire safety.
  • Fuel handling.
  • Manufacturer requirements.

This demonstrates the importance of integrating environmental management with health and safety in one practical plan.

How Should Generators Be Included in the HSE Plan?

The generator should not appear in the Health, Safety and Environment Plan only under a general heading such as “site equipment.”

The plan may address:

Environmental Risks

  • Noise.
  • Exhaust emissions.
  • Fuel spills.
  • Maintenance waste.
  • Impact on neighboring areas.

Health and Safety Risks

  • Fuel and flammable materials.
  • Hot surfaces.
  • Electricity.
  • Vehicle movement during refueling.
  • Maintenance hazards.
  • Emergency situations.
  • Unauthorized access.

Control Measures

  • Location selection.
  • Restricted areas.
  • Maintenance.
  • Inspection.
  • Spill-containment equipment.
  • Barriers.
  • Fuel procedures.
  • Noise and exhaust monitoring.
  • Training.
  • Response to complaints and incidents.

SSG explains that HSE Plans include identifying and assessing occupational and environmental risks, developing preventive measures, organizing emergency response, training and awareness, and establishing monitoring and documentation systems.

Daily Temporary Generator Monitoring Template

Inspection Item What Should Be Reviewed? Action if an Observation Exists
Generator location No surrounding changes that increase impact Reassess location
Exhaust Direction, condition, and absence of unusual smoke Technical inspection and corrective action
Noise No noticeable abnormal change or complaint Inspect and measure if required
Vibration Unit and foundation remain stable Review isolation and fixing
Operating hours Consistent with schedule and actual need Reduce unnecessary operation
Acoustic enclosure Closed, intact, and unmodified Repair defects
Ventilation No blockage or abnormal overheating Review location or barrier
Fuel No leaks or stains Contain and address the condition
Surrounding area Clean and safe Clean and correct
Complaints No open complaint Investigate and document
Maintenance Record is up to date Schedule the required action

How Do You Respond to a Generator Noise Complaint?

Record the Complaint

Document:

  • Date and time of complaint.
  • Affected location.
  • Description of the problem.
  • Duration.
  • Whether the issue was noise, vibration, or both.
  • Which generators were operating.
  • Activity taking place at the time.

Inspect From the Receptor Location

Standing next to the generator is not enough.

The problem should be assessed from the location where the complaint originated, or a point that represents it as closely as possible.

Review Operating Conditions

Ask:

  • Was more than one generator operating?
  • Was the enclosure open for maintenance?
  • Did new mechanical noise appear?
  • Did night-time operation begin when it had not occurred previously?
  • Was a temporary barrier removed?
  • Did site activities change?

Implement an Initial Action

This may include:

  • Repairing the enclosure.
  • Changing operating hours.
  • Modifying the barrier.
  • Switching off an unnecessary unit.
  • Performing maintenance.
  • Conducting measurements where necessary.

Verify Closure

Do not consider the case closed simply because an action was implemented.

Return to the complaint location and verify the result, then record what was found.

How Do You Respond to an Exhaust-Odor Complaint?

First review:

  • Wind direction.
  • Exhaust pipe direction.
  • Engine condition.
  • Presence of visible smoke.
  • Proximity to air intakes.
  • Operating hours.
  • Presence of other nearby sources.

Then implement the appropriate action after identifying the cause.

The issue may be related to the generator itself, its location, changing weather conditions, or a door, window, or ventilation opening that has become active during a new project phase.

Therefore, the solution should not simply be reduced to “move the generator” without a practical assessment.

What Are the Risks of Ignoring the Impact of Temporary Generators?

Increased Neighbor Complaints

Repeated noise or odors may affect the relationship between the project and neighboring buildings even when generator operation is temporary.

Project Delays

Management may have to relocate equipment or urgently redesign arrangements if the generator location was not assessed in advance.

Increased Operational Risks

Improvised modifications to barriers or exhaust arrangements intended to solve a complaint quickly may create ventilation or safety problems.

Difficulty Demonstrating Compliance

Without operating, maintenance, complaint, and monitoring records, reviewing the project’s environmental performance becomes more difficult.

Higher Corrective Costs

Relocating a generator after electrical connections, barriers, and fuel arrangements have already been installed may cost more than selecting an appropriate location at the beginning.

Unmanaged Environmental Impacts

Noise, exhaust, and fuel spills may be managed as separate issues even though they originate from the same source and require one coordinated monitoring system.

Common Mistakes When Managing Temporary Generators

Selecting the Location Only Because It Is Close to the Electrical Panel

Technical efficiency matters, but nearby buildings, neighboring areas, exhaust, noise, and safety must also be reviewed.

Assuming Temporary Operation Does Not Require Assessment

A temporary generator may operate for many hours per day and continue for several months of the project.

Directing Exhaust Away From the Site but Toward the Neighbor

The objective is not only to remove exhaust from worker areas; the project must also understand where it will travel afterward.

Installing an Acoustic Barrier Without Assessing Ventilation

A noise-control solution may create an operating problem if it blocks generator cooling.

Ignoring Vibration

Users of a nearby building may feel vibration even when external noise does not appear particularly high.

Relying Only on Breakdown Maintenance

Preventive maintenance helps detect changes in noise and exhaust before they develop into complaints.

Failing to Record Operating Hours

It becomes difficult to analyze complaints if the team does not know which generator was operating and for how long.

Closing Complaints Without Verification

The result should be evaluated after the action rather than simply proving that the team made a modification.

What Should Be Reviewed Before Requesting Environmental Consultancy?

  • Type of activity and project.
  • Project location in Kuwait.
  • Implementation phase.
  • Duration for which the generator is required.
  • Number of generators.
  • Operating capacity of each unit.
  • Daily operating hours.
  • Need for night-time operation.
  • Location of each generator on the site plan.
  • Nearest occupied building.
  • Locations of offices, residences, and sensitive facilities.
  • Nearby air-intake openings.
  • Exhaust outlet direction.
  • Presence of an acoustic enclosure.
  • Type of foundation and vibration isolation.
  • Maintenance log.
  • Operating log.
  • Previous noise or odor complaints.
  • Previous measurements, if available.
  • Current HSE Plan.
  • Previous environmental studies.
  • Available environmental data.
  • Relevant regulatory requirements.
  • Potential environmental and operational risks.
  • Fuel storage and refueling arrangements.
  • Emergency procedures.

Practical Table to Help You Select the Appropriate Environmental Service

Project Situation Appropriate Service Practical Objective
New construction project HSE Plan preparation Identify generator risks and controls before operation
Generator near an occupied building Field environmental assessment Review noise, exhaust, and location
Repeated noise complaint Noise-source review and measurement Identify the cause of nuisance and corrective action
Exhaust complaint Location and operational emissions assessment Review exhaust direction and generator condition
Several temporary generators Environmental supervision Monitor operation and cumulative impact
Expansion of an existing facility HSE review Protect workers and neighboring areas during construction
Night-time operation Specialized environmental monitoring Reduce impact during sensitive periods
Industrial site Emissions and noise review Integrate the generator with other site sources
Fuel spills HSE assessment and response procedures Improve containment and handling
High complaint record Corrective-action audit Identify recurring causes and prevent recurrence

How Do You Choose an Environmental Consultancy Company in Kuwait?

Experience in Projects and Operating Sites

The consultant should understand that the generator is part of a wider site system that includes construction activities, offices, contractors, equipment, and neighboring areas that may change as the project progresses.

Understanding Kuwaiti Requirements

Applicable environmental requirements and regulations in Kuwait relating to air, noise, environmental management, and safety should be reviewed according to the nature of the project.

The Kuwait Environment Public Authority publishes separate executive regulations covering ambient air protection, environmental management, air quality, noise in indoor environments, worker safety, and other relevant environmental areas.

Ability to Conduct Measurement and Assessment

The existence of a complaint does not always mean that the source is already known.

An environmental consultancy company in Kuwait should be able to identify suitable inspection and measurement points when needed and relate the results to actual operating conditions.

Clear Methodology

The scope of work should clarify:

  • Which equipment will be reviewed?
  • Which sensitive receptors will be assessed?
  • What are the operating periods?
  • Are measurements required?
  • How will complaints be monitored?
  • What outputs are expected?
  • Who is responsible for implementing the recommendations?

Practical and Applicable Solutions

Not every project can move a generator a large distance away.

The solution may require a combination of location adjustment, barriers, operating hours, maintenance, and performance monitoring.

Understanding the Integration Between Environment and Safety

Changes to exhaust systems, barriers, or fuel areas should not solve an environmental issue while creating a new risk for workers.

How Can SSG Help Assess Temporary Generators?

SSG support can begin by reviewing the project location, generator positions, operating periods, and the nature of neighboring areas before defining the appropriate scope of service.

Support may include:

  • Inspecting generator locations.
  • Identifying sensitive areas and buildings.
  • Reviewing sources of noise and vibration.
  • Reviewing exhaust direction.
  • Assessing operating conditions.
  • Reviewing operating and maintenance records.
  • Conducting or coordinating environmental measurements where necessary.
  • Reviewing complaints from neighboring areas.
  • Identifying appropriate control measures.
  • Following up implementation.
  • Preparing environmental reports.
  • Integrating generators into the HSE Plan.
  • Defining fuel and spill-management procedures.
  • Training site teams.
  • Monitoring cases and corrective actions.

SSG’s Environmental Supervision for Construction and Development Projects service includes field monitoring of activities, measurements of noise, air quality, wind speed, and other environmental monitoring parameters, in addition to inspections and reporting.

SSG’s HSE Plan Preparation service also helps organize risk assessment, preventive measures, emergency response, training, monitoring, and documentation so that the generator is managed as part of the overall project system rather than as an isolated piece of equipment.

Steps to Request Environmental Consultancy From SSG

  1. Contact the SSG Team

Explain the issue or project stage: a new generator, noise complaint, exhaust odor, night-time operation, or a need to update the HSE Plan.

  1. Send Project Information

You may provide:

  • Site plan.
  • Generator location.
  • Photographs of the area.
  • Generator capacity.
  • Operating hours.
  • Nearest buildings.
  • Maintenance and complaint records.
  • Current HSE Plan.
  1. Review the Nature of the Activity

The relationship between the generator, neighboring areas, operating conditions, and project phases is analyzed.

  1. Determine the Appropriate Service

The project may require:

  • A specific location review.
  • Noise measurement.
  • Environmental supervision.
  • Emissions assessment.
  • HSE Plan update.
  • A combination of these services.
  1. Conduct the Inspection or Study

The location, equipment, potential receptors, and project records are reviewed.

  1. Provide Findings and Recommendations

Actions are prioritized according to urgency, feasibility, and expected level of impact.

  1. Verify After Implementation

A follow-up review can confirm whether the modification resulted in actual improvement and did not create a new operational problem.

Frequently Asked Questions About Assessing the Impact of Temporary Generators on Neighboring Areas in Kuwait

What Are the Most Important Factors When Assessing the Impact of Temporary Generators on Neighboring Areas in Kuwait?

The main factors include generator location, distance from buildings, exhaust direction, air-intake openings, generator capacity, operating hours, noise and vibration, wind direction, and maintenance condition.

The nature of neighboring areas should also be reviewed. Residences, offices, or sensitive facilities may require more detailed monitoring than an industrial site located relatively far from receptors.

Is There One Safe Distance Between a Generator and a Building?

It is not preferable to use one general distance for all projects without assessing the specific situation.

The appropriate distance depends on generator design, exhaust outlet, ventilation, capacity, noise level, building characteristics, air intakes, barriers, and applicable requirements.

The location should therefore be evaluated as a complete system rather than relying on distance alone as evidence that the impact is acceptable.

How Can Temporary Generator Noise Be Reduced?

Start by increasing separation from sensitive areas, using a generator fitted with a suitable acoustic enclosure, installing properly designed barriers, using vibration isolators, carrying out maintenance, and reducing unnecessary operation.

Operating hours may also be adjusted where project requirements allow.

If complaints continue, noise measurements may be required at points representative of the affected area so that the source can be assessed more accurately.

How Can Generator Exhaust Be Prevented From Affecting a Building?

The process starts with location selection and reviewing the exhaust pipe direction in relation to doors, windows, air-intake openings, and gathering areas, while also considering wind movement.

Maintenance should be kept up to date and unusual smoke should be investigated.

Random modifications to the exhaust system are not recommended because manufacturer requirements, safety, and generator technical performance must be considered alongside environmental objectives.

Does a Temporary Generator Always Require Noise or Emissions Measurements?

Not necessarily.

The required level of monitoring depends on generator capacity, location, operating duration, nature of neighboring areas, environmental and contractual requirements, and whether complaints or signs of impact exist.

Site inspection and records may be sufficient in some cases, while others may require specialized measurements.

This should be determined after reviewing project details and applicable requirements.

Should Generators Be Included in the HSE Plan?

Yes. When generators form part of project activities, the HSE Plan should address their relevant risks, including electricity, fuel, fire, maintenance, noise, exhaust, and spills.

Inspection procedures, responsibilities, emergency arrangements, training, and documentation should also be defined.

The level of detail depends on the number of units, project size, operating duration, and site-related risks.

What Should a Project Do When a Complaint Is Received From a Neighbor?

The project should record the time, location, and nature of the complaint, then review which generators were operating, weather conditions, exhaust direction, and equipment condition.

After identifying the likely cause, an appropriate measure should be implemented, such as maintenance, modifying operations, adjusting the barrier, or changing the location.

The result should then be verified from a point representing the affected area.

The important objective is to close the underlying cause, not simply record that the complaint was “handled.”

When Does an Assessment of the Impact of Temporary Generators on Neighboring Areas in Kuwait Require Specialized Consultancy?

Specialized consultancy can be useful when a generator is close to an occupied building, when night-time operation is required, when repeated noise or exhaust complaints occur, when several generators are operating, or when the true source of the problem is difficult to determine.

It is also useful before selecting a generator location in a new project because adjusting the arrangement at an early stage is usually more practical than redesigning it after operation begins.

Contact SSG for Environmental Consultancy

If you are planning to install temporary generators near buildings or need an assessment of the impact of temporary generators on neighboring areas in Kuwait after noise or exhaust complaints have appeared, you can contact SSG for an initial assessment of your project requirements.

The initial assessment can help determine whether the project requires a review of the generator location, noise or air-quality measurements, improvements to operating and maintenance procedures, an HSE Plan update, or more comprehensive field environmental supervision.